Multistate Bar Examination Practice Question

What describes the characteristics of a valid liquidated damages provision in a contract?

  • A clause specifying damages agreed upon at the time of contracting for harm that may be difficult to quantify.

  • A provision adjusting damages based on actual losses after a breach.

  • A provision requiring one party to pay an amount unrelated to the harm caused by a breach.

  • A clause intended to deter breaches through financial consequences.

Multistate Bar Examination
Contracts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot