PgMP Practice Question
A high-level program scope statement can be created without input from the sponsors or steering committee because strategic objectives remain stable.
True
False
A high-level program scope statement can be created without input from the sponsors or steering committee because strategic objectives remain stable.
True
False
Strategic objectives can shift based on factors the sponsors and steering committee understand well. By involving these key stakeholders, the scope captures real-time priorities, constraints, and insights. Excluding them risks misalignment with the overall direction.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.