PgMP Practice Question

A program manager is finalizing a large system rollout. Some stakeholder groups have signed off, yet a few are requesting additional user support and documentation before taking ownership. Which action best ensures a complete transition so that these groups can sustain benefits without interruptions?

  • Obtain the sponsor’s formal email approval and transfer responsibilities from the program team once deliverables are migrated to production.

  • Obtain the sponsor’s formal email approval and conduct end user trainings.

  • Gather incomplete tasks into a new phase and allow each operational team to manage them after the program concludes.

  • Compile final acceptance details, confirm readiness, archive documentation, and transfer ownership to those operational teams.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot