PgMP Practice Question

A program manager is preparing to share the current progress with program leadership. Which approach best secures the permission needed to move forward into the next portion of the program?

  • Omit discussion of performance indicators until after the next portion has started

  • Highlight outcomes, budgeting needs, and potential risks in relation to the organization’s goals

  • only a) and b)

  • Give a detailed technical analysis of each minor project change within the program

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot