PgMP Practice Question

A program manager is responsible for a program aimed at reducing operational costs through the implementation of automated processes. Midway through the program, the manager observes that the cost savings are not meeting the projected targets. What should the program manager do to address this issue?

  • Continue monitoring the situation without implementing changes, anticipating future improvements in cost savings.

  • Perform a variance analysis to determine the reasons for the cost savings shortfall and implement corrective measures.

  • Inform stakeholders about the shortfall and explore options to achieve the original targets.

  • Reevaluate the benefits realization plan and adjust cost-saving targets accordingly.

PgMP
Benefits Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot