A program manager is tasked with launching a new CRM program. To obtain initial validation and approval from the executive sponsor, what should the program manager establish first?
A risk management plan
A project schedule with task assignments
A stakeholder communication strategy
A high-level road map with milestones and preliminary estimates
Creating a high-level road map with milestones and preliminary estimates provides a clear overview of the program’s trajectory and resource requirements, which is essential for obtaining executive approval.
Developing a project schedule, risk management plan, or stakeholder communication strategy comes after securing initial approval.
Reference: PgMP ECO, Task 2 - Strategic Program Alignment Establish a high-level road map with milestones and preliminary estimates to obtain initial validation and approval from the executive sponsor.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are milestones in a program roadmap?
Open an interactive chat with Bash
Why are preliminary estimates important for obtaining approval?
Open an interactive chat with Bash
What does strategic program alignment mean?
Open an interactive chat with Bash
PgMP
Strategic Program Alignment
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access