After a program has been delivered, which plan is crucial for ensuring the continued realization of its benefits?
Quality management plan
Transition plan to operations
Sustainment plan
Communication plan
After a program has been delivered, which plan is crucial for ensuring the continued realization of its benefits?
Quality management plan
Transition plan to operations
Sustainment plan
Communication plan
The correct answer is 'Sustainment plan' because it specifically outlines the processes, measures, metrics, and tools necessary to maintain and manage benefits after program completion. While a 'Transition plan to operations' focuses on moving deliverables to operational use, it does not comprehensively cover the ongoing management and continued realization of benefits. The other options, 'Communication plan' and 'Quality management plan,' do not address the sustainment of program benefits.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.