PgMP Practice Question

During a final session with stakeholders, a program manager shares updated metrics and encourages new insights. Which approach best supports the incorporation of this information into organizational knowledge for future initiatives?

  • Share key performance results with relevant participants, record discussions and recommendations in a main repository, and link the updated documents to existing program archives

  • Provide selected survey feedback to internal management and schedule another meeting at a later point to discuss performance outcomes

  • Document the discussion in the meeting minutes and file them away for reference.

  • Focus on cost data during the discussion, postpone collecting feedback from non-managerial team members until follow-up emails are sent

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot