PgMP Practice Question

During a phase gate review, what is the primary activity that program management should perform to ensure alignment with program objectives?

  • Compile and archive project documentation for future reference.

  • Evaluate project performance and decide whether to continue to the next phase.

  • Provide training sessions for team members on updated processes.

  • Redistribute resources among various projects based on needs.

PgMP
Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot