PgMP Practice Question

During a program review, the program manager notices that two ongoing projects have overlapping resource requirements. What action should the program manager take to capture this synergy and update the benefits realization plan?

  • Reallocate resources to the overlapping projects and update the benefits realization plan accordingly

  • Terminate one of the overlapping projects to eliminate the resource conflict

  • Ignore the overlap and focus on individual project objectives without altering the benefits realization plan

  • Report the resource overlap to the steering committee without making any changes to the program plan

PgMP
Benefits Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot