PgMP Practice Question

During a program, your sponsor insists on completing the final milestone two months sooner without adjusting the deliverables. Which approach helps align the sponsor’s perception with the program’s constraints?

  • Conduct a detailed assessment of the sponsor’s request and discuss practical trade-offs to reach a shared agreement on timeline adjustments

  • Postpone necessary workshops and reassign current resources to meet the new date without explaining any potential impact to the sponsor

  • Implement the requested schedule changes and inform other stakeholders after the revised plan is confirmed

  • Accept the sponsor’s shortened milestone timeline, then ask the sponsor to address any unforeseen issues if they occur

PgMP
Stakeholder Engagement
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot