During the development of a program closeout plan, which activity should the program manager prioritize to ensure effective knowledge transfer?

  • Allocating additional resources to remaining program activities

  • Documenting lessons learned and archiving program documentation

  • Launching new projects within the program

  • Initiating a change request for program scope