Which approach strengthens collaboration among different project teams by centralizing oversight, managing cross-project dependencies, and aligning outcomes to strategic objectives? Choose from the following options
Scope, schedule and budget baselines
An integrated plan defining governance, resource usage, and baselines for various efforts
A specialized matrix that details staff assignments across multiple projects
A consolidated document listing each project’s completed tasks
An integrated plan outlines guidelines and governance methods, sets scope, budget, timelines, and addresses cross-project resource and risk management, ensuring all contributing teams remain aligned with overarching goals. A staff assignment matrix focuses primarily on roles without providing a holistic oversight mechanism. A record of completed tasks lacks the forward-looking structure essential for ongoing coordination. The 3 baselines alone dont align outcomes to program objectives, their integration with management plans, assumptions, constraints and risks are equally important
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is an integrated plan in project management?
Open an interactive chat with Bash
What are project governance methods?
Open an interactive chat with Bash
How do cross-project dependencies affect project management?
Open an interactive chat with Bash
PgMP
Program Life Cycle Management
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access