PgMP Practice Question
Which research method is most appropriate for quantifying the financial benefits expected by program stakeholders?
Stakeholder interviews
High-level cost-benefit analysis
SWOT analysis
Gantt chart creation
Which research method is most appropriate for quantifying the financial benefits expected by program stakeholders?
Stakeholder interviews
High-level cost-benefit analysis
SWOT analysis
Gantt chart creation
High-level cost-benefit analysis is the correct answer because it specifically involves quantifying financial benefits, which aligns with the requirements of Task 6. The other options focus on different aspects of program management and do not directly address the quantification of financial benefits.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.