PgMP Practice Question
Which technique modifies tasks in a schedule so that assignments do not exceed capacity for staff or equipment?
Resource leveling
Tailoring constraints
Lessons learned documentation
Risk register updates
Which technique modifies tasks in a schedule so that assignments do not exceed capacity for staff or equipment?
Resource leveling
Tailoring constraints
Lessons learned documentation
Risk register updates
Resource leveling adjusts tasks to avoid staff overload by shifting work and balancing tasks. Tracking potential issues, capturing lessons, or adjusting constraints does not systematically align tasks with workforce capacity.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.