PgMP Practice Question

You are a program manager tasked with establishing the program management plan and schedule for a new program that includes multiple projects. To effectively forecast, monitor, and identify variances during execution, what should your primary focus be?

  • Develop individual project schedules independently to maintain project autonomy.

  • Focus on creating a comprehensive quality management plan for the program.

  • Delegate the creation of supporting plans to individual project managers without centralized oversight.

  • Integrate plans for constituent projects and create supporting plans for quality, risk, communication, and resources.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot