PgMP Practice Question

You are managing a marketing technology upgrade consisting of multiple sub-projects. Recent performance data shows that one sub-project’s costs have exceeded its plan, yet it is delivering advanced features ahead of schedule. Some team members believe these features will contribute more benefit to the overall program. Which action provides a more accurate understanding of this sub-project’s impact on the total program?

  • Apply financial restrictions to all sub-projects to compensate for cost overruns among a few deliverables

  • Transfer tasks across sub-projects while bypassing the standard approval procedure

  • Summarize cost and schedule data for that sub-project to see if resources can be repositioned in other project areas

  • Evaluate cost, schedule, scope, resource usage, and quality in a consolidated display to see whether the added features offset the extra costs

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot