PgMP Practice Question

You are managing a program consisting of several software development projects that are all scheduled to start simultaneously. You've noticed that multiple projects require the same specialized developers, leading to potential resource conflicts. Which of the following actions best optimizes the program management plan to maximize productivity and synergies among the constituent projects?

  • Consider adjusting the program budget to hire additional specialized developers for projects.

  • Reallocate the specialized developers to projects based on priority and timeline for balanced resource distribution.

  • Assign additional general developers to each project to compensate for the lack of specialized resources.

  • Delay the start of some projects until sufficient specialized developers are available.

PgMP
Program Life Cycle Management
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot