PgMP Practice Question

You have been selected to lead a multi-department initiative at your organization. Some individuals have collaborated on similar efforts in the past and express hesitation about potential resource conflicts. You want to gather data as part of your stakeholder engagement plan. Which approach would be appropriate to capture useful input from these individuals?

  • Submit an online survey to relevant stakeholders, then finalize the plan based on the collected feedback

  • Create a single-page outline of key milestones and seek alignment through subsequent meetings

  • Collect feedback from their previous project work, conduct targeted interviews, and consolidate findings in the plan

  • Consult with the primary sponsor to address concerns

PgMP
Stakeholder Engagement
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot