CompTIA Project+ PK0-005 Practice Question

A company is undertaking a complex project that requires frequent customer feedback and iterative releases. The project scope is expected to evolve over time, and the team values high levels of collaboration and flexibility. Which project management methodology is BEST suited for this project?

  • Kanban

  • Scrum

  • PRINCE2

  • Waterfall