CompTIA Project+ PK0-005 Practice Question

A project manager has completed the implementation of a new company-wide software application. Despite the successful technical deployment, many employees are reluctant to transition to the new application, preferring to stick with the old system. What action should the project manager take to promote the use of the new application among employees?

  • Assign more technical staff to support the new application.

  • Document the employees' feedback and proceed.

  • Revert to the old system to maintain employee productivity.

  • Offer additional training sessions to enhance employee familiarity with the new application.

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot