CompTIA Project+ PK0-005 Practice Question

A project manager is addressing several issues that have arisen during a project. To prioritize these issues effectively, considering the scope of impact to the organization, which issue should be resolved first?

  • An application flaw exposing customer information.

  • A typo in the user interface that doesn't affect functionality.

  • A delay in generating an internal report used by a small team.

  • A deprecated feature scheduled for removal in the next update.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot