CompTIA Project+ PK0-005 Practice Question

A project manager is initiating a new project and wants to ensure that all team members understand the project goals and their specific responsibilities. Considering the differences in communication methods, which of the following is the BEST way to convey this information?

  • Email a comprehensive summary of the project and roles to the team members.

  • Place the project overview and team assignments on an internal website for team members to access.

  • Upload the project plan to a collaboration platform and notify team members to review it.

  • Schedule a face-to-face session to introduce the project and engage the team in discussions about their roles.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot