CompTIA Project+ PK0-005 Practice Question

A project manager is starting a new project that requires specialized software tools not currently available within the organization. What is the BEST action the project manager should take during the planning phase?

  • Plan additional training for the team to work without the specialized software.

  • Modify the project scope to eliminate the need for specialized software.

  • Negotiate contracts with software vendors for the required tools.

  • Conduct a preliminary procurement needs assessment for the specialized software tools.

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot