A project manager needs to determine the sequence of activities and identify task dependencies to calculate the critical path of the project. Which of the following tools would BEST help achieve this goal?
A project network diagram is the best tool for visualizing task sequences and dependencies, allowing the project manager to identify the critical path. Gantt charts display tasks over time but are less effective for showing detailed dependencies. Budget burndown charts focus on budget usage over time, and milestone charts highlight significant project events without detailing task dependencies.