A project manager needs to visualize the distribution of task completion times to identify patterns in the data. Which chart should the project manager use to represent this information?
A histogram is used to represent the frequency distribution of numerical data, such as task completion times. It displays data in contiguous intervals, allowing the project manager to see patterns and understand how the data is distributed across different ranges. A run chart displays data points over time but does not show frequency distributions. A scatter diagram shows the relationship between two variables, and a control chart is used to monitor process stability over time.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a histogram and how does it work?
Open an interactive chat with Bash
What are the differences among a histogram, run chart, and control chart?
Open an interactive chat with Bash
When should a project manager use a scatter diagram?