A project manager receives a change request to add a new feature to the project deliverables. What is the BEST initial action the project manager should take?
Forward the change request to the change control board for their input after initial review.
Consider the change request and evaluate its alignment with project objectives before planning updates.
Conduct an impact assessment to evaluate the potential effects on project scope, schedule, and budget.
Evaluate the change request for potential scope risks before making a decision.
The project manager should conduct an impact assessment to determine how the proposed change will affect the project's scope, schedule, budget, and resources. This assessment provides essential information for making an informed decision and for communicating with stakeholders. Evaluating alignment with project objectives is important but is part of the broader impact assessment process. Forwarding the change request to the change control board should occur after the project manager has conducted the assessment. Focusing only on potential scope risks narrows the assessment and may overlook other critical impacts.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is an impact assessment in project management?
Open an interactive chat with Bash
What are project objectives and why are they important?
Open an interactive chat with Bash
What role does the change control board play in project management?