A project manager receives a deliverable from a vendor but discovers it does not meet the project's specifications. What is the BEST action for the project manager to take in this situation?

  • Accept the deliverable to avoid project delays.

  • Proceed with the project and document the issue.

  • Request the vendor to address the discrepancies.

  • Modify the deliverable internally to meet specifications.

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot