CompTIA Project+ PK0-005 Practice Question
A project manager wants to determine if project spending aligns with the budgeted plan. Which metric should they use?
Cost variance
Schedule variance
Quality variance
Scope variance
A project manager wants to determine if project spending aligns with the budgeted plan. Which metric should they use?
Cost variance
Schedule variance
Quality variance
Scope variance
Cost variance measures the difference between the actual cost incurred and the budgeted cost of work performed. It indicates whether the project is under or over budget at a given point in time. Schedule variance assesses the project's progress against the planned schedule, focusing on time rather than cost. Quality variance and scope variance are not standard metrics for evaluating cost performance in project management.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.