CompTIA Project+ PK0-005 Practice Question

Alex is a project manager overseeing a software development project with a tight deadline. During the project, a critical technical problem arises that the development team cannot resolve within the planned timeframe. This issue risks delaying the project deliverables. What is the best course of action for Alex to take to manage this issue?

  • Adjust the project scope to exclude the problematic component.

  • Communicate the issue to the appropriate stakeholders according to the escalation process.

  • Postpone dealing with the issue until the team has more time.

  • Assign additional resources from the team to try to fix the problem quickly.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot