Alex is managing a project that involves updating the company's website and launching a new marketing campaign. The project team decides to update the website before launching the marketing campaign to ensure that potential customers see the new design. However, from a technical standpoint, the marketing campaign could be launched before the website update, as there is no technical dependency between these tasks. The team's decision is based on their preferred approach and marketing strategy.

What type of dependency exists between the website update and the marketing campaign in this scenario?

  • Discretionary dependency

  • External dependency

  • Mandatory dependency

  • Internal dependency

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot