Assigning project resources is not required before developing a project schedule during the planning phase.
True
False
Assigning project resources is not required before developing a project schedule during the planning phase.
True
False
This statement is false. Assigning project resources is a necessary step before developing the project schedule. Knowing the availability and allocation of resources is crucial for creating an accurate and realistic schedule. Without assigning resources first, the schedule may not reflect actual capabilities and timelines.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.