CompTIA Project+ PK0-005 Practice Question

During a mobile app development project, a stakeholder requests a new feature that was not included in the original project scope. What should the project manager do first in response to this request?

  • Implement the new feature to accommodate the stakeholder's needs

  • Assess the necessity of the request and decide on its priority

  • Discuss the potential inclusion of the feature with the project team

  • Document the change request and conduct a preliminary review

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot