CompTIA Project+ PK0-005 Practice Question

During a project, significant changes to the project's scope have occurred due to external factors, causing major impacts on the schedule and budget. What should the project manager do to appropriately integrate these changes into the project management plan?

  • Make minor revisions to the existing baseline to accommodate the changes.

  • Adjust the project plan and establish a new baseline to reflect the major changes.

  • Reject the changes to maintain the original project objectives.

  • Update the project plan but continue to track progress against the original baseline.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot