During a project, team members are unsure about important deadlines and key dates. What should have been established during the planning phase to prevent this issue?
Establishing milestones in the project schedule allows team members to be aware of important deadlines and key dates. Milestones serve as significant points in the project timeline that help the team track progress toward critical events or deliverables. While a communication plan outlines how project information will be shared, it does not specifically detail deadlines. The project charter authorizes the project but does not provide detailed scheduling information. A risk management plan focuses on identifying and mitigating risks, not on establishing key dates.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What are project milestones?
Open an interactive chat with Bash
How are milestones established in a project schedule?
Open an interactive chat with Bash
Why is it important to have milestones in project management?