During the initiation phase of a project, what is the BEST way for a project manager to assess the level of impact and engagement of the project's stakeholders?

  • Send a survey to stakeholders asking about their expectations.

  • Conduct a stakeholder analysis to evaluate their power and interest.

  • Hold a kickoff meeting to introduce the project to stakeholders.

  • Create a stakeholder register that lists all stakeholders and their contact information.

CompTIA Project+ PK0-005
Project Life Cycle Phases
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot