CompTIA Project+ PK0-005 Practice Question

During the planning phase of a project, the project manager learns that there are new industry regulations that could affect the project outcomes. What is the BEST action for the project manager to take?

  • Expect the project team to adjust to the regulations without changing the plan.

  • Ignore the regulations since they were not in place during project initiation.

  • Assess the impact of the new regulations and update the project plan accordingly.

  • Proceed with the original plan and address regulations during project execution.

CompTIA Project+ PK0-005
Basics of IT and Governance
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot