In earned value management, which metric is calculated by subtracting planned value (PV) from earned value (EV) and indicates whether a project is ahead or behind in terms of work progress against the baseline plan?

  • Estimate to Complete (ETC)

  • Variance at Completion (VAC)

  • Cost Variance (CV)

  • Schedule Variance (SV)