CompTIA Project+ PK0-005 Practice Question
In project-specific change control, which document is used to record and track change requests throughout the project?
Issue log
Risk register
Change control log
Meeting minutes
In project-specific change control, which document is used to record and track change requests throughout the project?
Issue log
Risk register
Change control log
Meeting minutes
The change control log is used to document and monitor all change requests during a project. It ensures each request is properly recorded, evaluated, and managed, allowing the project team to control changes to the project scope, schedule, and cost. While the issue log records problems that need resolution, and the risk register tracks potential risks, these documents do not specifically focus on change requests. Meeting minutes capture discussions and decisions from meetings but are not dedicated to tracking changes.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.