CompTIA Project+ PK0-005 Practice Question
In the change control process, the project manager must validate that the implemented change aligns with the approved change request and meets project objectives.
True
False
In the change control process, the project manager must validate that the implemented change aligns with the approved change request and meets project objectives.
True
False
This statement is True. After a change has been implemented, it is essential for the project manager to validate the implementation. This ensures that the change was executed correctly, aligns with what was approved by the change control board, and contributes positively towards achieving the project's objectives. Skipping this step could result in unnoticed errors or misalignments that may adversely affect the project's outcome.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.