CompTIA Project+ PK0-005 Practice Question
Which tool visually represents a project's schedule by displaying tasks as horizontal bars across a timeline?
Gantt chart
Fishbone diagram
Milestone chart
PERT chart
Which tool visually represents a project's schedule by displaying tasks as horizontal bars across a timeline?
Gantt chart
Fishbone diagram
Milestone chart
PERT chart
A Gantt chart displays tasks as horizontal bars along a timeline, illustrating their start and end dates. This visual representation helps in tracking project schedules and managing timelines effectively. A PERT chart focuses on task sequences and dependencies. A milestone chart highlights key events in a project. A fishbone diagram, or Ishikawa diagram, is used for root cause analysis, not for scheduling.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.