CompTIA Project+ PK0-005 Practice Question
Which type of chart displays project tasks along a timeline, illustrating their start and end dates as well as task dependencies?
Milestone chart
PERT chart
Budget burndown chart
Gantt chart
Which type of chart displays project tasks along a timeline, illustrating their start and end dates as well as task dependencies?
Milestone chart
PERT chart
Budget burndown chart
Gantt chart
A Gantt chart displays project tasks against a timeline, showing their start and end dates, durations, and dependencies between tasks. This visual representation helps in tracking the project schedule and managing resource allocation effectively. Milestone charts highlight significant events or deliverables but do not show task durations or dependencies. Budget burndown charts track the expenditure of project funds over time. PERT charts (Program Evaluation Review Technique) represent tasks and their sequences in a network diagram, focusing on task durations and dependencies without a timeline format.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All IT & Cybersecurity Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
Access our store with even bigger discounts than before.
Unlimited access to all performance questions and be prepared for the real thing.
All IT & Cybersecurity Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.