While analyzing risks on a project, the project manager notices that the occurrence of one risk could increase the chance of other risks happening, amplifying the overall effect on the project. Which qualitative risk analysis concept does this BEST describe?

  • Risk impact assessment

  • Interconnectivity

  • Detectability

  • Probability assessment