CompTIA Project+ PK0-005 Practice Question

You are managing a project, and during the implementation phase, a key component supplied by a vendor fails to meet quality standards, threatening the project's timeline. As a project manager, which action should you take to effectively address this issue?

  • Develop a plan to resolve the issue by analyzing its cause, assessing its priority based on severity and impact, and implementing appropriate actions.

  • Document the issue and continue with the project as planned.

  • Replace the vendor to minimize project delays.

  • Escalate the issue to the project sponsor and request additional resources.

CompTIA Project+ PK0-005
Project Management Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot