You are managing a project and have been tracking the financial performance using a budget burndown chart. Recently, you notice that the actual spending is consistently above the planned spending line. Which action should you take in response to this observation?
Adjust the budget to accommodate the higher spending
Investigate the overspending and adjust cost management strategies
Cut back on project activities to reduce costs
Expand the project scope to utilize additional resources
When the actual spending on a budget burndown chart exceeds the planned spending line, it indicates that the project is over budget. The appropriate action is to investigate the reasons for the cost overrun and implement cost control measures to realign spending with the budget. Adjusting cost management strategies helps address the underlying issues causing overspending. Simply adjusting the budget or project scope does not solve the problem and may lead to further budget discrepancies. Reducing project activities without proper analysis could negatively impact project deliverables.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a budget burndown chart?
Open an interactive chat with Bash
What are cost management strategies?
Open an interactive chat with Bash
Why shouldn't I just adjust the budget when spending is above the planned line?