CAPM Practice Question

A project manager finds that the project has an earned value (EV) of $120,000 and a planned value (PV) of $150,000 at a certain point in time. What does this tell the project manager about the project's schedule performance?

  • The project is ahead of schedule by $30,000.

  • The project is behind schedule by $30,000.

  • The project is over budget by $30,000.

  • The project is on schedule.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot