CAPM Practice Question
A project manager is defining a component at the lowest level of the WBS that can be estimated and managed. What is this component known as?
Milestone
Activity
Work Package
Deliverable
A project manager is defining a component at the lowest level of the WBS that can be estimated and managed. What is this component known as?
Milestone
Activity
Work Package
Deliverable
The work package is the lowest level of the Work Breakdown Structure (WBS) and represents a deliverable or project work component that can be scheduled, cost estimated, monitored, and controlled. Activities are specific tasks derived from work packages, deliverables are outcomes of project work, and milestones are significant points or events in the project timeline.
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
All Project Management Package plans include the following perks and exams .
Our pricing is simple. Full access to all certifications and exams in each package, for one price.
As many practice tests for as many topics as you want.
Use study mode non-stop, no limits.
Access to our AI assistant, Bash, trained to help you pass your exam.
Track your scores over time in study mode and report cards.
See how you improve over time, and where you need to focus.
All Project Management Package plans include unlimited access to the following study materials.
Create an account or sign in to access our study materials.