A project manager is implementing an agile approach for a software development project. The team needs to document project controls that allow for visibility into progress and impediments. Which artifact would be BEST for tracking daily progress and identifying obstacles?
The correct answer is the Daily Scrum board or Kanban board. In adaptive projects, visual boards are essential artifacts for documenting project controls because they provide real-time visibility into work progress, identify bottlenecks, and highlight impediments. Unlike other options, these boards are specifically designed for daily tracking and transparency.
The product backlog is focused on maintaining prioritized features, not daily tracking. While the burndown chart shows progress over time, it doesn't specifically highlight obstacles or impediments. The definition of done, while important for quality control, doesn't provide daily progress tracking or impediment identification.
Ask Bash
Bash is our AI bot, trained to help you pass your exam. AI Generated Content may display inaccurate information, always double-check anything important.
What is a Daily Scrum board or Kanban board?
Open an interactive chat with Bash
What are impediments in an Agile context?
Open an interactive chat with Bash
What is the difference between a product backlog and a Daily Scrum board?
Open an interactive chat with Bash
CAPM
Agile Frameworks/Methodologies
Your Score:
Report Issue
Bash, the Crucial Exams Chat Bot
AI Bot
Loading...
Loading...
Loading...
Project Management Package Join Premium for Full Access