CAPM Practice Question

A project manager is implementing an agile approach for a software development project. The team needs to document project controls that allow for visibility into progress and impediments. Which artifact would be BEST for tracking daily progress and identifying obstacles?

  • Definition of done

  • Product backlog

  • Daily Scrum board or Kanban board

  • Burndown chart