A project manager is overseeing a project that is experiencing an unexpected increase in defects during testing. To address this issue according to the quality management plan, what should the project manager do?

  • Increase the budget to hire more testers.

  • Perform a root cause analysis to identify underlying issues in the processes.

  • Extend the project schedule to allow for additional testing.

  • Reduce the project scope to minimize potential defects.

CAPM
Predictive, Plan-Based Methodologies
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot