CAPM Practice Question

A project manager is overseeing the development of a new software application where the requirements are not fully defined and are expected to evolve based on stakeholder feedback during the project. Which project management approach would be most suitable for this project?

  • Implement a predictive project management approach that relies on detailed upfront planning

  • Implement an adaptive project management approach that allows for evolving requirements

  • Implement an operational management approach to accommodate stakeholder feedback

  • Implement a hybrid project management approach combining predictive and adaptive methodologies

CAPM
Project Management Fundamentals and Core Concepts
Your Score:
Settings & Objectives
Random Mixed
Questions are selected randomly from all chosen topics, with a preference for those you haven’t seen before. You may see several questions from the same objective or domain in a row.
Rotate by Objective
Questions cycle through each objective or domain in turn, helping you avoid long streaks of questions from the same area. You may see some repeat questions, but the distribution will be more balanced across topics.

Check or uncheck an objective to set which questions you will receive.

Bash, the Crucial Exams Chat Bot
AI Bot